Intel Delays Mass Production of 10 nm CPUs to 2019
by Anton Shilov on April 27, 2018 12:20 PM ESTIntel on Thursday announced that it would delay mass production of its 10 nm processors from 2018 to 2019 due to yield issues. The company has claimed to be shipping some of its 10 nm chips in small volumes right now, but due to cost reasons the firm does not intend to initiate their high-volume manufacturing (HVM) at this time. Intel executives also stated that they are confident of their product roadmap and intend to launch Whiskey Lake and Cascade Lake products later this year.
Multipatterning Issues
Brian Krzanich, CEO of Intel, stated during a conference call with financial analysts:
“We are shipping [10-nm chips] in low volume and yields are improving, but the rate of improvement is slower than we anticipated. As a result, volume production is moving from the second half of 2018 into 2019. We understand the yield issues and have defined improvements for them, but they will take time to implement and qualify.”
Intel blames a very high transistor density and consequent heavy use of multipatterning for low yields. Brian Krzanich has said that in certain cases the company needs to use quad (4x), penta (5x), or hexa (6x) patterning for select features as they need to expose the wafer up to six times to “draw” one feature. This not only lengthens Intel’s manufacturing cycle (which by definition rises costs) and the number of masks it uses, but also has an effect on yields.
Intel’s 10 nm fabrication technology relies solely on deep ultraviolet (DUV) lithography with lasers operating on a 193 nm wavelength at this time. The company’s 7 nm manufacturing process will use extreme ultraviolet (EUV) lithography with laser wavelength of 13.5 nm for select layers, eliminating use of extreme multipatterning for certain metal layers. As it appears, right now Intel executives do not consider EUV technology ready for prime time in 2019, so the company’s engineers have to polish off the last DUV-only process (again) rather than jump straight to 7 nm.
10 nm Ramp in 2019
Intel does not elaborate whether it intends to ship (in volume) its 10 nm CPUs in the first half or the second half of 2019, but only says that the company’s engineers know the source of the yield problems and are working hard to fix them. As a result, it is pretty safe to assume that the actual ramp of Intel’s 10 nm production will begin towards the second half of next year.
“We are going to start that ramp as soon as we think the yields are in line, so I said 2019,” Mr. Krzanich noted. “We did not say first or second half, but we will do it as quickly as we can, based on the yield.”
In a bid to stay competitive before its 10-nm CPUs ship in the H2 2019 – H1 2020 (production ramp takes time, bigger processors will launch later than smaller parts), Intel plans to release another generation of products made using its 14 nm process tech. This generation of chips includes Whiskey Lake products for client PCs and Cascade Lake for the datacenter, and both are scheduled for release later this year.
Questions Remain: 10 nm Slip from 2016
Intel’s 10 nm manufacturing process has a long history of delays and without any doubts this transition has been the hardest in the company’s history. Let's do a quick recap.
Intel First Production |
|
1999 | 180 nm |
2001 | 130 nm |
2003 | 90 nm |
2005 | 65 nm |
2007 | 45 nm |
2009 | 32 nm |
2011 | 22 nm |
2014 | 14 nm |
2016 | |
2017 | |
2018 | 10 nm? |
2019 | 10 nm! |
Intel originally planned to commence shipments of its first processors made using their 10 nm fabrication technology in the second half of 2016. The first rumors about Intel’s problems with the tech started to spread in early 2015 as the company delayed the installation of equipment needed for its 10 nm manufacturing process. Then, in July 2015, the chip giant confirmed intentions to postpone 10 nm HVM from H2 2016 to H2 2017 due to difficulties incurred by multipatterning. Instead, the company promised to release its Kaby Lake products with enhancements and made using a refined 14 nm process (known as 14+ later).
Over the course of 2016 and 2017 we learned that Intel was prepping Cannon Lake (mobile, entry-level desktops), Ice Lake (higher-end client PCs, servers), and Tiger Lake chips on their 10 nm node. We also heard about various problems that Intel faced with its 10 nm technology, but the company refuses to comment on them. The chipmaker did demonstrate a system running a mobile Cannon Lake SoC at CES 2017, with a promise to release this processors late that year. Somewhere along the line, both Ice Lake and Tiger Lake slipped to 2018, which was partly confirmed by the launch of the Coffee Lake CPU made using a revamped 14 nm (14++) in late 2017.
Intel officially introduced the 10 nm fabrication process at IEDM 2017 and said it was on track to start shipments of CNL CPUs in early 2018. In January this year Intel confirmed that they had started to ship Cannon Lake processors in small volumes, but never elaborated. We have since learned that these were CNL-U parts in uninspiring 2+2 and CNL 2+0 configurations, however so far Intel has refused to state who the customer is or where anyone can buy them, despite repeated requests for this information.
Being a very large company, Intel has a multifaceted strategy that spans across product lines and generations. Right now, Intel is battling with yield issues that plague its Cannon Lake product family and the first-gen 10 nm manufacturing process. There are other 10 nm products in the pipeline that are to be made using a refined fabrication technology (such as 10+, 10++). It is pretty obvious that Intel will learn how to improve its 10 nm yields with the CNL lineup, but what remains to be seen is how significantly the delays of this product family affect launch schedules of its successors. Despite Intel's statements, there is outside discussion that Intel could decide to switch right to 7 nm, bypassing 10 nm altogether.
Related Reading
- Intel's 10nm Briefly Appears: Dual Core Cannon Lake in Official Documents
- Intel Mentions 10nm, Briefly
- Intel Displays 10nm Wafer, Commits to 10nm ‘Falcon Mesa’ FPGAs
- Intel at ISSCC 2015: Reaping the Benefits of 14nm and Going Beyond 10nm
Sources: Intel, SeekingAlpha
155 Comments
View All Comments
FunBunny2 - Monday, April 30, 2018 - link
"I don't believe monopoly tactics will work ever again."he says as Trumpism marches us rapidly to oligarchs.
jjj - Friday, April 27, 2018 - link
Intel pulls a Tesla, except their CEO doesn't sleep on the fab's floor.10nm was announced at IDC 2013 and targeted for 2015.
Shipping low volumes means sampling, in Intel's proprietary language.
This is big news for AMD, gives them a lot of extra room to gain share in all areas. Just this new delay could easily mean 3-4 extra billion in revenue for AMD in the next 5 years.
akamateau - Friday, April 27, 2018 - link
Hmmm...Will AnandTech actually Benchmark 7nm AMD Ryzen and EPYC CPU's vs 14nm Intel CPU's?
I expect that the on-line media WILL NEVER show Intel in a bad light.
MrSpadge - Friday, April 27, 2018 - link
> I expect that the on-line media WILL NEVER show Intel in a bad light.Too young to remember the Pentium 4 days?
HStewart - Saturday, April 28, 2018 - link
Don't worry about that forums of tech sites - do a very good job on doing that - but do seriously real customers care about that.Ninjawithagun - Friday, April 27, 2018 - link
Funny how this is 'okay' and not really a big deal for Intel to announce such a delay. Had it been AMD, the virtual CPU sky would be falling as we speak. Perspective...sponsored and paid for by Intel.Maxiking - Friday, April 27, 2018 - link
Damn, in every article about Intel so many amd butthurts, that HPET still hurts.eva02langley - Monday, April 30, 2018 - link
HPET is just showing something is damn wrong with Intel architecture. It is not affecting AMD at all. Also, we don't even know if this is an issue with just old games.By the way, enjoy your 1080p @ 144Hz bench for < 3% of newer built.
MrSpadge - Friday, April 27, 2018 - link
Dude, stop these stupid accusations. Did you notice that you're typing this on the website which is accused of producing the best (=unfair) Ryzen 2 results?Hifihedgehog - Friday, April 27, 2018 - link
Meanwhile...“AMD Sampling 7nm Zen 2 CPUs Later This Year, Launching in 2019“