Putting It All Together

Finally, we have been able to offer you a comparison of real OEM servers. In this article, we tried some new approaches with our testing methods: we measured and compared response times and energy consumption, instead of the usual focus on "throughput" and "maximum/idle power". It is important to take a step back and look at all our benchmark data from the point of view of a server buyer.

Let's start with the quad Xeon 7500 server: the SGI Altix UV 10 or QSSC-4R. Based on our performance numbers alone, we felt that one quad Xeon 7500 server could replace two or more dual Xeon servers as the performance/price was right. The price is about 2.5x higher than a dual Xeon, but you get twice the performance, more expandibility (PCIe and DIMM slots), and superior RAS as bonus. Remember, a Xeon MP with a price/performance ratio that could rival that of a dual Xeon was a first.

But the appearance of the Dell R815 and the high energy consumption make the SGI / QSSC server retreat to its typical target (and very profitable) markets: ERP, databases with large memory footprints where RAS is not a bonus but the top priority. The performance was a pleasant surprise and the power consumption of CPUs was decent. Make sure you populate at least 32 DIMMs, as bandwidth takes a dive at lower DIMM counts.

The power consumption of the platform, especially looking at the idle numbers, remains a weak spot. We know that scalability and availability come with a price, but three times higher energy consumption than a dual socket server is too much to convince us that the quad Xeon platform is an attractive virtualization building block.

The HP Proliant DL380 G7 surprised with better than expected energy consumption and some really clever engineering (CPU cage, cold redundancy, energy management...). The high single threaded performance of the Xeon X5670 leads to low response times in many real world circumstances. At high loads, it is outperformed by the Dell R815 that is hardly more expensive.

With 80% higher DIMM counts and 80% to 85% higher throughput, the Dell PowerEdge R815 surpasses the rival HP DL380 G7 by a large margin, while at the same time costing only 20-30% more and needing just as much rack space. That is amazing value. While the price/performance ratio blew us away, we were also hoping that a single R815 could beat the performance/watt ratio of two HP DL380 G7s by a significant margin. That would have been the cherry on the cake, but it did not happen.

The server is not too blame; rather, the CPUs consume more than the ACP ratings that AMD mentions everywhere. The truth is that the CPUs at high load consume much closer to their TDP numbers than ACP ones. However, the performance per watt ratio of the complete server is still competitive. The lower single-thread performance per core is a disadvantage in applications with complex webpages. We would avoid the low end Opteron 6100s.

The bottom line is that Dell's R815 can replace two HP DL380 G7s at a much lower investment cost, with about the same energy costs and lower management costs. Having to manage half as much physical servers should after all also lower the operation costs. Dell's PowerEdge R815 materializes AMD's promise of the "Value 4P server".

 

My special thanks goes out to Tijl Deneut for his benchmarking assistance.

Response Times In Summary, Pros and Cons
Comments Locked

51 Comments

View All Comments

  • pablo906 - Saturday, September 11, 2010 - link

    High performance Oracle environments are exactly what's being virtualized in the Server world yet it's one of your premier benchmarks.

    /edit should read

    High performance Oracle environments are exactly what's not being virtualized in the Server world yet it's one of your premier benchmarks.
  • JohanAnandtech - Monday, September 13, 2010 - link

    "You run highly loaded Hypervisors. NOONE does this in the Enterprise space."

    I agree. Isn't that what I am saying on page 12:

    "In the real world you do not run your virtualized servers at their maximum just to measure the potential performance. Neither do they run idle."

    The only reason why we run with highly loaded hypervisors is to measure the peak throughput of the platform. Like VMmark. We know that is not realworld, and does not give you a complete picture. That is exactly the reason why there is a page 12 and 13 in this article. Did you miss those?
  • Per Hansson - Sunday, September 12, 2010 - link

    Hi, please use a better camera for pictures of servers that costs thousands of dollars
    In full size the pictures look terrible, way too much grain
    The camera you use is a prime example of how far marketing have managed to take these things
    10MP on a sensor that is 1/2.3 " (6.16 x 4.62 mm, 0.28 cm²)
    A used DSLR with a decent 50mm prime lens plus a tripod really does not cost that much for a site like this

    I love server pron pictures :D
  • dodge776 - Friday, September 17, 2010 - link

    I may be one of the many "silent" readers of your reviews Johan, but putting aside all the nasty or not-so-bright comments, I would like to commend you and the AT team for putting up such excellent reviews, and also for using industry-standard benchmarks like SAPS to measure throughput of the x86 servers.

    Great work and looking forward to more of these types of reviews!
  • lonnys - Monday, September 20, 2010 - link

    Johan -
    You note for the R815:
    Make sure you populate at least 32 DIMMs, as bandwidth takes a dive at lower DIMM counts.
    Could you elaborate on this? We have a R815 with 16x2GB and not seeing the expected performance for our very CPU intensive app perhaps adding another 16x2GB might help
  • JohanAnandtech - Tuesday, September 21, 2010 - link

    This comment you quoted was written in the summary of the quad Xeon box.

    16 DIMMs is enough for the R815 on the condition that you have one DIMM in each channel. Maybe you are placing the DIMMs wrongly? (Two DIMMs in one channel, zero DIMM in the other?)
  • anon1234 - Sunday, October 24, 2010 - link

    I've been looking around for some results comparing maxed-out servers but I am not finding any.

    The Xeon 5600 platform clocks the memory down to 800MHz whenever 3 dimms per channel are used, and I believe in some/all cases the full 1066/1333MHz speed (depends on model) is only available when 1 dimm per channel is used. This could be huge compared with an AMD 6100 solution at 1333MHz all the time, or a Xeon 7560 system at 1066 all the time (although some vendors clock down to 978MHz with some systems - IBM HX5 for example). I don't know if this makes a real-world difference on typical virtualization workloads, but it's hard to say because the reviewers rarely try it.

    It does make me wonder about your 15-dimm 5600 system, 3 dimms per channel @800MHz on one processor with 2 DPC @ full speed on the other. Would it have done even better with a balanced memory config?

    I realize you're trying to compare like to like, but if you're going to present price/performance and power/performance ratios you might want to consider how these numbers are affected if I have to use slower 16GB dimms to get the memory density I want, or if I have to buy 2x as many VMware licenses or Windows Datacenter processor licenses because I've purchased 2x as many 5600-series machines.
  • nightowl - Tuesday, March 29, 2011 - link

    The previous post is correct in that the Xeon 5600 memory configuration is flawed. You are running the processor in a degraded state 1 due to the unbalanced memory configuration as well as the differing memory speeds.

    The Xeon 5600 processors can run at 1333MHz (with the correct DIMMs) with up to 4 ranks per channel. Going above this results in the memory speed clocking down to 800MHz which does result in a performance drop to the applications being run.
  • markabs - Friday, June 8, 2012 - link

    Hi there,

    I know this is an old post but I'm looking at putting 4 SSDs in a Dell poweredge and had a question for you.

    What raid card did you use with the above setup?

    Currently a new Dell poweredge R510 comes with a PERC H700 raid card with 1GB cache and this is connect to a hot swap chassis. Dell want £1500 per SSD (crazy!) so I'm looking to buy 4 intel 520s and setup them up in raid 10.

    I just wanted to know what raid card you used and if you had a trouble with it and what raid setup you used?

    many thanks.

    Mark
  • ian182 - Thursday, June 28, 2012 - link

    I recently bought a G7 from www.itinstock.com and if I am honest it is perfect for my needs, i don't see the point in the higher end ones when it just works out a lot cheaper to buy the parts you need and add them to the G7.