Adjusting Trajectory & Slipping Schedule

Carrell didn’t believe in building big chips anymore. It wasn’t that it was too difficult, it’s that it took too long for a $600 GPU to turn into a $200 GPU. AMD believed that the most important market was the larger (both in quantity and revenue) performance mainstream segment.

Rather than making the $200 - $300 market wait for new technology, Carrell wanted to deliver it there first and then scale up/down to later address more expensive/cheaper markets.

The risk in RV770 was architecture and memory technology. The risk in RV870 was architecture and manufacturing process, the latter which was completely out of AMD’s control.

Early on Carrell believed that TSMC’s 40nm wasn’t mature enough and that when it was ready, its cost was going to be much higher than expected. While he didn’t elaborate on this at the time, Carrell told me that there was a lot of information tuning that made TSMC’s 40nm look cheaper than it ended up being. I'll touch on this more later on in the article.

Carrell reluctantly went along with the desire to build a 400+ mm2 RV870 because he believed that when engineering wakes up and realizes that this isn’t going to be cheap, they’d be having another discussion.

In early 2008, going into Februrary, TSMC started dropping hints that ATI might not want to be so aggressive on what they think 40nm is going to cost. ATI’s costs might have been, at the time, a little optimistic.

Engineering came back and said that RV870 was going to be pretty expensive and suggested looking at the configuration a second time.

Which is exactly what they did.

The team met and stuck with Rick Bergman’s compromise: the GPU had to be at least 2x RV770, but the die size had to come down. ATI changed the configuration for Cypress (high end, single GPU RV870) in March of 2008.

And here’s where the new ATI really showed itself. We had a company that had decided to both 1) not let schedule slip, and 2) stop designing the biggest GPU possible. Yet in order to preserve the second belief, it had to sacrifice the first.

You have to understand, changing a chip configuration that late in the game, 1.5 years before launch, screws everything up. By the time RV770 came out, 870 was set in stone. Any changes even a year prior to that resets a lot of clocks. You have to go back and redo floorplan and configuration, there’s a lot of adjusting that happens. It takes at least a couple of weeks, sometimes a couple of months. It impacted schedule. And ATI had to work extremely hard to minimize that where possible. The Radeon HD 5870 was around 30 - 45 days late because of this change.

Remember ATI’s nothing-messes-with-schedule policy? It took a lot of guts on the part of the engineering team and Rick Bergman to accept a month+ hit on redesigning RV870. If you don’t show up to the fight, you lose by default, and that’s exactly what ATI was risking by agreeing to a redesign of Cypress.

This is also super important to understand, because it implies that at some point, NVIDIA made a conscious decision to be late with Fermi. ATI wasn’t the only one to know when DX11/Windows 7 were coming. NVIDIA was well aware and prioritized features that delayed Fermi rather than align with this market bulge. GPUs don’t get delayed without forewarning. AMD risked being late in order to make a smaller chip, NVIDIA risked being late to make a bigger one. These two companies are diverging.


The actual RV870

Engineering was scrambling. RV870 had to be a lot smaller yet still deliver 2x the computational power of RV770. Features had to go.

The Other Train - Building a Huge RV870 Carrell Loses His Baby: Say Goodbye to Sideport
Comments Locked

132 Comments

View All Comments

  • simtex - Sunday, February 21, 2010 - link

    Excellent article ;) Insider info is always interesting, makes me a little more happy about my -50% AMD stocks, hopefully they will one go up again.
  • NKnight - Wednesday, February 17, 2010 - link

    Great read.
  • - Friday, February 19, 2010 - link


    you should write a (few)book(s); of course in multi eReader formats

    asH
  • - Saturday, February 20, 2010 - link

    Nvidia blames sales shortfall on TSMC

    http://www.eetimes.com/news/latest/showArticle.jht...">http://www.eetimes.com/news/latest/show...E1GHPSKH...

    one dot you didnt connect in the article was AMD's foundry experience, which gives AMD a big advantage over NVIDIA; must have been an oversight?

    asH
  • truk007 - Tuesday, February 16, 2010 - link

    These articles are why I keep coming here. The other sites could learn a lesson here.

  • dstigue1 - Tuesday, February 16, 2010 - link

    I think the title says it all. But to add I also like the technical level. You can understand it with some cursory knowledge in graphics technology. Wonderfully written.
  • sotoa - Tuesday, February 16, 2010 - link

    Excellent work and very insightful indeed!
  • juzz86 - Tuesday, February 16, 2010 - link

    An amazing read Anand, I can wholeheartedly understand why you'd enjoy your dinners so much. One reader said that these were among the best articles on the site, and I have to agree. Inside looks into developments in the industry like this one are the real hidden gems of reviewing and analysis today. You should be very proud. Thanks again. Justin.
  • talon262 - Tuesday, February 16, 2010 - link

    Hell of an article...congrats to Anand for putting it out there and to the team at ATI for executing on some hard-learned lessons. Since I have a 4850 X2, I'm most likely going to sit Evergreen out (the only current ATI card that specs higher than my 4850 X2 (other than the 4970 X2) is Hemlock/5970 and Cypress/5870 would be a lateral move, more or less); while I run Win7, DX11 compatibilty is not a huge priority for me right this moment, but I will use the mid-range Evergreen parts for any systems I'll build/refurb over the next few months.

    Northern Islands, that has got me salivating...

    (Crossposted at Rage3D)
  • Peroxyde - Monday, February 15, 2010 - link

    Thanks for the great article. Do you have any info regarding ATI's commitment to the Linux platform? I used to see in Linux forums about graphics driver issues that ATI is the brand to avoid. Is it still the case?